The Building and Construction Industry Security of Payment Act 2009 (SA) (“the Act”) is often referred to as a ‘pay now, argue later’ procedure entitling contractors and subcontractors to progress payments and quick resolution when disputes arise. However, there remains unfamiliarity with the processes, and key timing for those processes, when dealing with disputed payment claims made under the Act. Here’s a quick (as opposed to complete) list of the events (and associated timing) that unfold following receipt of a progress payment issued pursuant to the Act.

Progress Payments

  1. A progress payment can be a:
    • Final payment;
    • One-off payment; or
    • Milestone payment.
  2. The amount of a progress payment is determined in accordance with the contract, but if the contract does not specify the amount it will be assessed in terms of the value of the work carried out.

Payment Claim

  1. To invoke the Act the person entitled to a progress payment must serve a payment claim on the person responsible for payment. That claim must:
    • identify the work to which the progress payment relates;
    • indicate the amount of the progress payment claimed to be due; and
    • state that they are doing so under the Act. For example:

“This is a payment claim under the Building and Construction Security of Payments Act 2009 (SA)…”

Payment Schedule

  1. A person served with a payment claim may respond by providing a payment schedule either within 15 business days or the period specified in the contract, whichever comes first.
  2. The payment schedule must:
    • identify the relevant payment claim;
    • identify the amount the person served with the claim proposes to pay; and
    • if the amount proposed to be paid is less than the payment claim, indicate why it is less and the reasons for withholding payment.

Payment

  1. Where a person fails:
    • to respond to a payment claim within the earlier of the time required by the contract or 15 days; and/or
    • to pay the amount due and payable in accordance with either the progress claim or the payment schedule,

the progress claim can be recovered as a due debt in a court.

If proceedings are commenced, the recipient of the progress claim is not entitled to bring a cross-action (i.e. for defective works) or raise a defence (other than that the progress claim does not comply with the Act and therefore, no liability to make payment has arisen). Remember, it is a ‘pay now, argue later’ scheme.

Adjudication

  1. Where:
    • a payment claim is disputed and a payment schedule is provided; or
    • payment is not made in accordance with a payment schedule by the due date; or
    • no payment schedule is provided, but the claimant otherwise decides, (as an alternative to proceedings)
    • where a payment schedule is provided that proposes to pay less than the claimed debt, within 15 days of receiving the payment schedule; or
    • where a payment schedule is provided, but the payment is not made by the due date, within 20 days after the due date of the payment.
  1. Where no payment schedule is provided in response to a progress claim, the claimant can make an application for adjudication provided the claimant has notified the other party of his/her intention to make such an application:
    • within 20 business days immediately following the due date for payment of the progress claim; and
    • the other party was given an opportunity to provide a payment schedule within 5 business days of being notified by the claimant.
  2. Following this, the people involved will be notified of the adjudicator’s appointment.

Response

  1. The person served with an adjudication application claim can lodge a response within five business days of receiving the application or within two business days of receiving notice of the adjudicator’s appointment.
  2. The response:
    • must be in writing;
    • must identify the relevant adjudication application;
    • may contain submissions relevant to the response; and
    • must be served on the person making the payment claim.
  3. However, you cannot submit a response if you did not provide a payment schedule following receipt of the payment claim, or, alternatively, following receipt of notice of the claimant’s intention to refer the matter to adjudication.
  4. The response cannot introduce new reasons for withholding payment, which further highlights the importance of preparing a payment schedule.

Obligations

  1. The adjudicator is required to make a decision generally within ten business days of the response.
  2. If the adjudicator determines an amount is payable, it must be paid within 5 days of the adjudicator’s decision.
  3. If the adjudicated amount is not paid in the timeframe, the person claiming payment may request an adjudication certificate and serve notice of their intention to suspend the work (or supply of goods) to which the adjudicated amount relates.
  4. The person owed the payment can file an adjudication certificate with the Court as a judgment which is enforceable.
  5. If the person against whom a judgment is entered chooses to challenge that judgment, that person:
    • cannot bring a cross claim against the person seeking judgment;
    • cannot raise a defence in relation to matters arising from the construction contract;
    • cannot challenge the adjudicator’s decision; and
    • is required to pay the unpaid amount into the Court as security pending the final determination in those proceedings.
  6. Once the adjudicated amount is paid, the aggrieved person can institute court proceedings to claim against the other party for any set off (by way of repayment) and/or costs of the defective works in the ordinary course.

For further information or advice on disputes under the Building and Construction Industry Security of Payment Act 2009 (SA) contact Joe De Ruvo.

This communication provides general information which is current as at the time of production. The information contained in this communication does not constitute advice and should not be relied upon as such. Professional advice should be sought prior to any action being taken in reliance on any of the information. Should you wish to discuss any matter raised in this article, or what it means for you, your business or your clients' businesses, please feel free to contact us.

For more information, please contact...

Joe De Ruvo

View Profile →

Related Articles

View All News
March 08, 2024 In Pursuit of Justice: The Women’s Rights Journey
Dispute Resolution & Insolvency
December 20, 2023 Residential Tenancies Act Amendments Navigating the Impact on Landlords
Property
October 30, 2023 DW Fox Tucker Lawyers Gains an Engineering Edge with the Arrival of Rising Star
Firm News Dispute Resolution & Insolvency
September 26, 2023 DW Fox Tucker Lawyers Welcomes Helene Chryssidis as Director
Firm News Dispute Resolution & Insolvency
September 22, 2023 Navigating the Building & Construction Industry Security of Payment Act 2009 (SA)
Dispute Resolution & Insolvency
July 12, 2023 How to Freeze Crypto Assets in South Australia
Dispute Resolution & Insolvency
June 30, 2021 Two of a Kind: Federal Court Refuses to See Double in Case of Identical Pharmaceutical Products
Dispute Resolution & Insolvency
June 30, 2021 When are Directors Liable for Misleading or Deceptive Conduct, Passing off, Trade Mark Infringement or Unconscionable Conduct?
Corporate & Commercial Dispute Resolution & Insolvency Intellectual Property (IP)
June 30, 2021 Jurisdiction Clauses: A Primer
Dispute Resolution & Insolvency
June 30, 2021 An Insurer’s Duty of Utmost Good Faith
Dispute Resolution & Insolvency Insurance & Risk Management
December 16, 2020 King Reigns All: High Court Decides Holding Companies May Be Held Accountable for Subsidiary Company Actions
Corporate & Commercial Dispute Resolution & Insolvency
December 16, 2020 Building and Construction Contracts: The Importance of Good Contract Administration
Corporate & Commercial Dispute Resolution & Insolvency Property
December 16, 2020 Debt Recovery and Maximising Costs Recoveries
Dispute Resolution & Insolvency
December 16, 2020 A Win for Women in Pelvic Mesh Class Action - for the Moment …
Dispute Resolution & Insolvency
December 16, 2020 Onus of Proof in Tax Disputes
Dispute Resolution & Insolvency Tax
September 30, 2020 COVID-19: Retail and Commercial Leasing Emergency Relief Prescribed Period 2
Property
September 09, 2020 COVID-19: Retail and Commercial Leasing Emergency Relief Extension
Property
May 18, 2020 COVID-19 Regulations for Commercial Tenancies
Property
May 13, 2020 State Government Announces Changes Affecting Commercial Tenancies
Property
April 23, 2020 COVID-19: Changes in the Court System You Need to Know About
Dispute Resolution & Insolvency